Back to projects

Data Warehouse

DATADelayed

Consolidate product analytics into a governed warehouse with dbt models.

Apr 13, 2026Sep 19, 2026·Data·13/39 tasks done
PNDWHKLSEN+1
34%complete

Completion

34%

Overall progress

Tasks done

5/19

14 remaining

Story points

19/73

Completed of planned

Team

6

Contributors

Delivery health
Progress, budget burn and key dates
Progress34%
Budget spent$26,010 of $85,000 · 31%
Start

Apr 13

Due

Sep 19

Duration

159d

Milestones
1 of 4 complete
  • Kickoff & discovery

    Apr 12, 2026

  • Design sign-off

    May 28, 2026

  • Beta release

    Jul 15, 2026

  • General availability

    Sep 30, 2026

Recent activity
Latest updates on this project
  1. DW

    Daniel Weber moved Migrate legacy invoice PDFs to In Review

    24m ago
  2. PN

    Priya Nair completed Add SSO / SAML provisioning

    1h ago
  3. PN

    Priya Nair commented on Wire up Slack notifications

    3h ago
  4. HK

    Hannah Kim started work on Add optimistic UI to mutations

    5h ago
  5. PN

    Priya Nair marked milestone Kickoff & discovery as complete

    Yesterday
Team
Lead and collaborators
PN

Priya Nair

Project lead

DW

Daniel Weber

Backend Engineer

HK

Hannah Kim

Customer Success Lead

LS

Lucas Silva

Data Analyst

EN

Emma Novak

Frontend Engineer